NPO was brought on to provide shielding for Mechanical Penetrations Room No. 1 at Davis-Besse. This room featured a variety of pipe runs with many valves, bends, and reductions throughout as well as many hot spots. Using a combination of drawing information and practical measurements taken on site, NPO provided a shielding package using T-Flex […]
Byron had an issue with an ARGOS Zeus unit in the main exit area of the RCA. Background gamma radiation from a line in the overhead was shining down and causing false alarms on the gamma detectors to the point of making the unit inoperable. Due to the position of the Argos unit it was […]
NPO offers a number of engineering services to validate the integrity and performance of our shielding. We are the industry experts when it comes to aiding nuclear power plants design new and unique shielding and pride ourselves on our technical expertise. We want to act as part of your team to not only ensure the […]
NPO worked closely with AVANTech in designing a set of three shielded casks that reduced dose from 26,000-30,000 mRem/hr (260,000-300,000 μSv/hr) to less than 60 mRem/hr (600 μSv/hr) on contact. Two casks were utilized with one as a spare. Each shielded cask housed one of their Solids Collection Filter canisters for torus water/sludge filtration at […]
For BWR plants, shielding the inner bellows is particularly challenging. During refueling operation the concrete shield plugs above the reactor well are removed and replaced by water. This water filled gap becomes a source for both radiation and contamination. NPO designed a specialized system to address the concerns with shielding this area. Some of the […]